CIMFASO and Intercem signed a contract for the provision of a cement grinding plant consisting entirely of new plant components. The grinding plant features a milling output of 135 tonnes per hour. The contract included engineering work, the supply of mechanical and electrical plant components as well as spare parts, shipping to Burkina Faso, and supervision for plant assembly and commissioning.
The 4.6 x 16.0 m ball mill, featuring a mill drive output of 4500 kW, plus a range of plant components were delivered as early as December 2013. At the start of 2014, additional deliveries for steel construction, building cladding and sheet steel construction were then provided by Intercem.
The cement grinding plant was commissioned in early 2015 and has operated without problems ever since.
The 4.6 x 16.0 m ball mill, featuring a mill drive output of 4500 kW, plus a range of plant components were delivered as early as December 2013. At the start of 2014, additional deliveries for steel construction, building cladding and sheet steel construction were then provided by Intercem.The cement grinding plant was commissioned in early 2015 and has operated without problems ever since.